Deliverable Due Dates

  1. 9/19: Refined requirements specification (3.4-3.9).

  2. 9/24: Scenarios (2.2).

  3. 9/19: Primary class list (3.10).

  4. 10/1: Class diagrams (3.10).

  5. 10/1: Use case descriptions and diagrams (3.10).

  6. 10/3: Structured walk-through (in class) (3.8).

  7. 10/8: Object diagrams (5.3).

  8. 10/8: Revised class diagrams (5.2, 5.3).

  9. 10/15: User interface mock-ups.

  10. 10/8: State machines (4.7).

  11. 10/15: Collaboration diagrams (5.3).

  12. 10/22: Sequence diagrams (5.3).

  13. 10/22: Object diagrams (5.3).

  14. 10/29: Refined class diagrams (5.2, 5.3).

  15. 10/29: Class skeletons (5.2).

  16. 10/31: Informal walk-through/design refinement (in class).

  17. 10/29: Implementation plan (7.4, 7.5).

  18. 11/24: Source code.

  19. 11/5: Test plan (8.4, 8.7).

  20. 12/1: Test analysis report (8.5).

  21. 12/10: System Integration (7.4).

  22. 12/12: Code Freeze (no more work permitted).

  23. Final: System delivery and demo.